See the work. Claim the completed scope.
Select a sequence in the model or schedule. Use the planned view to follow the baseline, then switch to actual status to accept completion gates and compare earned labor with hours spent. Changes are for exploration and are not saved.
Setup
Loading the 3D model…
Drag to rotate · scroll to zoom · click steel to select
Baseline schedule · working days
Sequence 4
Sequence budget
All five operations · MH
Earned hours
Actual hours
Eight-sequence sample · schematic geometry · illustrative budgets and follow-on timing. Erection durations use picks by work class and one raising gang. Follow-on bars show assumed timing, without checking crew capacity, access, crane reach or stability.