Planning the work

From project information to field production.

Working notes on steel erection planning, work packaging, crane operations, production measurement and project controls.

  1. File access
  2. Work packages
  3. Tons and picks
  4. Production rates
  5. Resource loading
  6. Estimating feedback

Current series

Building the production model

Each note continues the same argument: project information becomes useful when it is connected directly to how the work will be performed.

Note 01 · Work packaging

Organize the dashboard around the work

A dashboard becomes more useful when its structure matches the way the field experiences the project.

Read note →
Note 02 · Production measurement

We do not make tonnage in the field

Two work packages can contain the same tonnage and require very different amounts of effort.

Read note →
Next note · Labor productivity

Breaking MH/ton apart

Picks per ton describes the work mix. Man-hours per pick describes how the crew is moving through it.

MH/ton = MH/pick × picks/ton
Where the series is going

From measurement to a resource-loaded schedule

Turn planned picks, expected throughput and crew configuration into durations that can be measured and tested.

Part of the ongoing series